What is the difference between Actual Cost and Earned Value? (2024)

  1. All
  2. IT Services
  3. Software Project Management

Powered by AI and the LinkedIn community

1

What is Actual Cost?

2

What is Earned Value?

3

How to compare AC and EV?

4

How to use AC and EV to measure project performance?

Be the first to add your personal experience

5

How to use AC and EV to forecast project outcomes?

6

What are the benefits and limitations of AC and EV?

7

Here’s what else to consider

Be the first to add your personal experience

If you are a software project manager, you probably know that measuring the progress and performance of your project is essential for delivering value to your stakeholders. But how do you compare what you have spent so far with what you have achieved? Two common metrics that can help you answer this question are Actual Cost (AC) and Earned Value (EV). In this article, you will learn what these terms mean, how they are calculated, and how they are used to assess your project's status and health.

Top experts in this article

Selected by the community from 5 contributions. Learn more

What is the difference between Actual Cost and Earned Value? (1)

Earn a Community Top Voice badge

Add to collaborative articles to get recognized for your expertise on your profile. Learn more

  • Shreekant Karpe Program delivery manager / Agile Project Manager | SSM® 6| CSM® | PRINCE2® Foundation / Practitioner | ASP.Net MVC…

    What is the difference between Actual Cost and Earned Value? (3) 1

What is the difference between Actual Cost and Earned Value? (4) What is the difference between Actual Cost and Earned Value? (5) What is the difference between Actual Cost and Earned Value? (6)

1 What is Actual Cost?

Actual Cost (AC) is the amount of money that you have spent on your project until a certain point in time. It includes all the direct and indirect costs that are related to the project work, such as labor, materials, equipment, software, travel, and overhead. AC is also known as Actual Cost of Work Performed (ACWP) or simply Cost. You can calculate AC by adding up all the invoices, receipts, and expenses that you have incurred for your project.

Add your perspective

Help others by sharing more (125 characters min.)

2 What is Earned Value?

Earned Value (EV) is the amount of money that you have earned from your project until a certain point in time. It represents the value of the work that you have completed, based on the planned budget and scope of your project. EV is also known as Budgeted Cost of Work Performed (BCWP) or simply Value. You can calculate EV by multiplying the percentage of work completed by the planned budget for that work. For example, if you have completed 50% of a task that has a budget of $10,000, your EV for that task is $5,000.

Add your perspective

Help others by sharing more (125 characters min.)

  • Shreekant Karpe Program delivery manager / Agile Project Manager | SSM® 6| CSM® | PRINCE2® Foundation / Practitioner | ASP.Net MVC development | Aspiring DevOps engineer and currently specializing in Docker and Kubernetes orch
    • Report contribution

    Earned value (EV) is the value of the work that has been effectively completed so far, using your initial cost estimations as a valuation factor and not the actual cost. In simple terms: EV is the money you should have spent on the work that was actually done.To calculate EV, you need to multiply the percentage of work completed by the total budget. For example, if the budget is $100,000 and 50% of the work is done, the EV is $50,000. So, EV = 50% x $100,000 = $50,000.

    Like

3 How to compare AC and EV?

By comparing AC and EV, you can determine whether your project is on budget, over budget, or under budget. If AC and EV are equal, it means that you have spent exactly what you have earned, and your project is on budget. If AC is less than EV, it means that you have spent less than what you have earned, and your project is under budget. If AC is more than EV, it means that you have spent more than what you have earned, and your project is over budget. The difference between AC and EV is called Cost Variance (CV), and it can be expressed as CV = EV - AC. A positive CV indicates that your project is under budget, while a negative CV indicates that your project is over budget.

Add your perspective

Help others by sharing more (125 characters min.)

  • Shreekant Karpe Program delivery manager / Agile Project Manager | SSM® 6| CSM® | PRINCE2® Foundation / Practitioner | ASP.Net MVC development | Aspiring DevOps engineer and currently specializing in Docker and Kubernetes orch
    • Report contribution

    AC and EV measures the performance and progress of a project. To compare AC and EV, you can use the following formulas:Cost Variance (CV) = EV - AC; Cost Performance Index (CPI) = EV / AC. A positive CV means the project is under budget, while a negative CV means the project is over budget. A CPI greater than 1 means the project is under budget, while a CPI less than 1 means the project is over budget. For example, suppose a project has a budget of $100,000 and 50% of the work is done. The AC so far is $60,000 and the EV is $50,000. The CV and CPI are:CV = EV - AC = $50,000 - $60,000 = -$10,000CPI = EV / AC = $50,000 / $60,000 = 0.83; This Means project is over budget by $10,000 and has a cost efficiency of 83%.

    Like

4 How to use AC and EV to measure project performance?

Besides comparing AC and EV, you can also use them to measure how efficiently and effectively your project is performing. By dividing EV by AC, you can obtain a ratio called Cost Performance Index (CPI), which indicates how much value you are getting for every dollar spent. A CPI of 1 means that you are getting exactly what you paid for, and your project is on budget. A CPI greater than 1 means that you are getting more value than what you paid for, and your project is under budget. A CPI less than 1 means that you are getting less value than what you paid for, and your project is over budget. The higher the CPI, the better your project's cost performance.

Add your perspective

Help others by sharing more (125 characters min.)

5 How to use AC and EV to forecast project outcomes?

Another way to use AC and EV is to forecast the future outcomes of your project, such as the total cost and the completion date. By extrapolating the current trends of AC and EV, you can estimate how much more money you will need to finish your project, and how long it will take. One method to do this is called Estimate at Completion (EAC), which is the expected total cost of your project at the end. You can calculate EAC by dividing the planned budget of your project by the CPI. For example, if your project has a planned budget of $100,000 and a CPI of 0.8, your EAC is $125,000. This means that you will need $25,000 more than what you originally planned to complete your project.

Add your perspective

Help others by sharing more (125 characters min.)

  • Shreekant Karpe Program delivery manager / Agile Project Manager | SSM® 6| CSM® | PRINCE2® Foundation / Practitioner | ASP.Net MVC development | Aspiring DevOps engineer and currently specializing in Docker and Kubernetes orch
    • Report contribution

    To use AC and EV to forecast project outcomes, you need to calculate the following indicators:Cost Variance (CV) = EV - ACCost Performance Index (CPI) = EV / ACSchedule Variance (SV) = EV - PVSchedule Performance Index (SPI) = EV / PVEstimate at Completion (EAC) = BAC / CPIEstimate to Complete (ETC) = EAC - ACVariance at Completion (VAC) = BAC - EACThese indicators help you compare the planned and actual values of cost and schedule, and predict the final cost and duration of the project. They also help you identify potential issues or risks, and take corrective actions if needed.

    Like

6 What are the benefits and limitations of AC and EV?

Using AC and EV can help you monitor and control your project's cost and value, and provide you with valuable insights and feedback to make informed decisions and adjustments. AC and EV can also help you communicate your project's status and health to your stakeholders, and demonstrate your accountability and transparency. However, AC and EV also have some limitations that you should be aware of. For instance, AC and EV do not reflect the quality or the customer satisfaction of your project's deliverables, which are also important aspects of value. AC and EV also depend on the accuracy and reliability of your project's plan, scope, and budget, which may change over time due to risks, changes, and uncertainties. Therefore, you should not rely solely on AC and EV, but use them in conjunction with other metrics and indicators that capture the full picture of your project's performance and value.

Add your perspective

Help others by sharing more (125 characters min.)

  • Shreekant Karpe Program delivery manager / Agile Project Manager | SSM® 6| CSM® | PRINCE2® Foundation / Practitioner | ASP.Net MVC development | Aspiring DevOps engineer and currently specializing in Docker and Kubernetes orch
    • Report contribution

    Some of the benefits and limitations of AC and EV are:AC and EV help you compare the planned and actual values of cost and schedule, and predict the final cost and duration of the project. They also help you identify potential issues or risks, and take corrective actions if needed.AC and EV require accurate and timely data collection and analysis, which can be challenging and time-consuming for complex or large-scale projects. They also depend on the quality and reliability of the baseline plan, which may change due to scope creep, change requests, or unforeseen events.AC and EV are not sufficient to measure the quality, customer satisfaction, or business value of the project. They only focus on the quantitative aspects of the project.

    Like

7 Here’s what else to consider

This is a space to share examples, stories, or insights that don’t fit into any of the previous sections. What else would you like to add?

Add your perspective

Help others by sharing more (125 characters min.)

Software Project Management What is the difference between Actual Cost and Earned Value? (48)

Software Project Management

+ Follow

Rate this article

We created this article with the help of AI. What do you think of it?

It’s great It’s not so great

Thanks for your feedback

Your feedback is private. Like or react to bring the conversation to your network.

Tell us more

Report this article

More articles on Software Project Management

No more previous content

  • You're facing budget overruns on your project. How can you satisfy stakeholders without sacrificing quality?
  • Your team is divided on project priorities. How do you ensure resources are allocated effectively?
  • Balancing competing stakeholder demands in Agile software projects: Can you prioritize tasks effectively?
  • Your team is struggling with adapting to scope changes. How will you get them on board?
  • Balancing user feedback and technical constraints in your project. Can you find the sweet spot for success? 4 contributions

No more next content

See all

Explore Other Skills

  • IT Strategy
  • System Administration
  • Technical Support
  • Cybersecurity
  • IT Management
  • IT Consulting
  • IT Operations
  • Data Management
  • Information Security
  • Information Technology

More relevant reading

  • Control Engineering You’re working on a project with limited resources. How can you make sure you meet your deadlines?
  • Project Management You’re a project manager. How do you ensure your projects stay within budget?
  • Project Management How do you assess project progress using earned value analysis?
  • Project Management What is the most effective way to estimate project value and return on investment?

Are you sure you want to delete your contribution?

Are you sure you want to delete your reply?

What is the difference between Actual Cost and Earned Value? (2024)
Top Articles
Dubai’s VARA: Two Years As World’s First Virtual Asset Regulator
5 Types of Water Filters and How They Work
Craigslist Warren Michigan Free Stuff
55Th And Kedzie Elite Staffing
Craigslist Monterrey Ca
Pangphip Application
Uihc Family Medicine
Unblocked Games Premium Worlds Hardest Game
What Are the Best Cal State Schools? | BestColleges
Robinhood Turbotax Discount 2023
Www Craigslist Louisville
2022 Apple Trade P36
Moviesda Dubbed Tamil Movies
Clafi Arab
Gw2 Legendary Amulet
CSC error CS0006: Metadata file 'SonarAnalyzer.dll' could not be found
Anki Fsrs
Declan Mining Co Coupon
Sotyktu Pronounce
Aita Autism
Slope Unblocked Minecraft Game
Cooktopcove Com
How to Store Boiled Sweets
Inside the life of 17-year-old Charli D'Amelio, the most popular TikTok star in the world who now has her own TV show and clothing line
Arre St Wv Srj
Van Buren County Arrests.org
[Cheryll Glotfelty, Harold Fromm] The Ecocriticism(z-lib.org)
Theater X Orange Heights Florida
Greenville Sc Greyhound
Reser Funeral Home Obituaries
Danielle Moodie-Mills Net Worth
Primerica Shareholder Account
Vlocity Clm
Elanco Rebates.com 2022
Fandango Pocatello
Culver's Hartland Flavor Of The Day
Serenity Of Lathrop - Manteca Photos
Litter-Robot 3 Pinch Contact & DFI Kit
Priscilla 2023 Showtimes Near Consolidated Theatres Ward With Titan Luxe
Parent Portal Pat Med
My Eschedule Greatpeople Me
8 4 Study Guide And Intervention Trigonometry
Leland Westerlund
Jackerman Mothers Warmth Part 3
Euro area international trade in goods surplus €21.2 bn
Steam Input Per Game Setting
2000 Fortnite Symbols
Zom 100 Mbti
Ocean County Mugshots
4015 Ballinger Rd Martinsville In 46151
Loss Payee And Lienholder Addresses And Contact Information Updated Daily Free List Bank Of America
Bloons Tower Defense 1 Unblocked
Latest Posts
Article information

Author: Mr. See Jast

Last Updated:

Views: 5742

Rating: 4.4 / 5 (55 voted)

Reviews: 94% of readers found this page helpful

Author information

Name: Mr. See Jast

Birthday: 1999-07-30

Address: 8409 Megan Mountain, New Mathew, MT 44997-8193

Phone: +5023589614038

Job: Chief Executive

Hobby: Leather crafting, Flag Football, Candle making, Flying, Poi, Gunsmithing, Swimming

Introduction: My name is Mr. See Jast, I am a open, jolly, gorgeous, courageous, inexpensive, friendly, homely person who loves writing and wants to share my knowledge and understanding with you.