- All
- IT Services
- Software Project Management
Powered by AI and the LinkedIn community
1
What is Actual Cost?
2
What is Earned Value?
3
How to compare AC and EV?
4
How to use AC and EV to measure project performance?
Be the first to add your personal experience
5
How to use AC and EV to forecast project outcomes?
6
What are the benefits and limitations of AC and EV?
7
Here’s what else to consider
Be the first to add your personal experience
If you are a software project manager, you probably know that measuring the progress and performance of your project is essential for delivering value to your stakeholders. But how do you compare what you have spent so far with what you have achieved? Two common metrics that can help you answer this question are Actual Cost (AC) and Earned Value (EV). In this article, you will learn what these terms mean, how they are calculated, and how they are used to assess your project's status and health.
Top experts in this article
Selected by the community from 5 contributions. Learn more
Earn a Community Top Voice badge
Add to collaborative articles to get recognized for your expertise on your profile. Learn more
- Shreekant Karpe Program delivery manager / Agile Project Manager | SSM® 6| CSM® | PRINCE2® Foundation / Practitioner | ASP.Net MVC…
1
1 What is Actual Cost?
Actual Cost (AC) is the amount of money that you have spent on your project until a certain point in time. It includes all the direct and indirect costs that are related to the project work, such as labor, materials, equipment, software, travel, and overhead. AC is also known as Actual Cost of Work Performed (ACWP) or simply Cost. You can calculate AC by adding up all the invoices, receipts, and expenses that you have incurred for your project.
Help others by sharing more (125 characters min.)
- Shreekant Karpe Program delivery manager / Agile Project Manager | SSM® 6| CSM® | PRINCE2® Foundation / Practitioner | ASP.Net MVC development | Aspiring DevOps engineer and currently specializing in Docker and Kubernetes orch
- Report contribution
Thanks for letting us know! You'll no longer see this contribution
Actual Cost (AC) is the total amount of money spent on a project or activity so far. To calculate AC, you must track and record all the expenses incurred for the project or activity, such as labor, materials, equipment, etc. To calculate EV, you need to multiply the percentage of work completed by the total budget. For example, if the budget is $100,000 and 50% of the work is done, the EV is $50,000.
LikeLike
Celebrate
Support
Love
Insightful
Funny
1
2 What is Earned Value?
Earned Value (EV) is the amount of money that you have earned from your project until a certain point in time. It represents the value of the work that you have completed, based on the planned budget and scope of your project. EV is also known as Budgeted Cost of Work Performed (BCWP) or simply Value. You can calculate EV by multiplying the percentage of work completed by the planned budget for that work. For example, if you have completed 50% of a task that has a budget of $10,000, your EV for that task is $5,000.
Help others by sharing more (125 characters min.)
- Shreekant Karpe Program delivery manager / Agile Project Manager | SSM® 6| CSM® | PRINCE2® Foundation / Practitioner | ASP.Net MVC development | Aspiring DevOps engineer and currently specializing in Docker and Kubernetes orch
- Report contribution
Thanks for letting us know! You'll no longer see this contribution
Earned value (EV) is the value of the work that has been effectively completed so far, using your initial cost estimations as a valuation factor and not the actual cost. In simple terms: EV is the money you should have spent on the work that was actually done.To calculate EV, you need to multiply the percentage of work completed by the total budget. For example, if the budget is $100,000 and 50% of the work is done, the EV is $50,000. So, EV = 50% x $100,000 = $50,000.
LikeLike
Celebrate
Support
Love
Insightful
Funny
3 How to compare AC and EV?
By comparing AC and EV, you can determine whether your project is on budget, over budget, or under budget. If AC and EV are equal, it means that you have spent exactly what you have earned, and your project is on budget. If AC is less than EV, it means that you have spent less than what you have earned, and your project is under budget. If AC is more than EV, it means that you have spent more than what you have earned, and your project is over budget. The difference between AC and EV is called Cost Variance (CV), and it can be expressed as CV = EV - AC. A positive CV indicates that your project is under budget, while a negative CV indicates that your project is over budget.
Help others by sharing more (125 characters min.)
- Shreekant Karpe Program delivery manager / Agile Project Manager | SSM® 6| CSM® | PRINCE2® Foundation / Practitioner | ASP.Net MVC development | Aspiring DevOps engineer and currently specializing in Docker and Kubernetes orch
- Report contribution
Thanks for letting us know! You'll no longer see this contribution
AC and EV measures the performance and progress of a project. To compare AC and EV, you can use the following formulas:Cost Variance (CV) = EV - AC; Cost Performance Index (CPI) = EV / AC. A positive CV means the project is under budget, while a negative CV means the project is over budget. A CPI greater than 1 means the project is under budget, while a CPI less than 1 means the project is over budget. For example, suppose a project has a budget of $100,000 and 50% of the work is done. The AC so far is $60,000 and the EV is $50,000. The CV and CPI are:CV = EV - AC = $50,000 - $60,000 = -$10,000CPI = EV / AC = $50,000 / $60,000 = 0.83; This Means project is over budget by $10,000 and has a cost efficiency of 83%.
Like
4 How to use AC and EV to measure project performance?
Besides comparing AC and EV, you can also use them to measure how efficiently and effectively your project is performing. By dividing EV by AC, you can obtain a ratio called Cost Performance Index (CPI), which indicates how much value you are getting for every dollar spent. A CPI of 1 means that you are getting exactly what you paid for, and your project is on budget. A CPI greater than 1 means that you are getting more value than what you paid for, and your project is under budget. A CPI less than 1 means that you are getting less value than what you paid for, and your project is over budget. The higher the CPI, the better your project's cost performance.
Help others by sharing more (125 characters min.)
5 How to use AC and EV to forecast project outcomes?
Another way to use AC and EV is to forecast the future outcomes of your project, such as the total cost and the completion date. By extrapolating the current trends of AC and EV, you can estimate how much more money you will need to finish your project, and how long it will take. One method to do this is called Estimate at Completion (EAC), which is the expected total cost of your project at the end. You can calculate EAC by dividing the planned budget of your project by the CPI. For example, if your project has a planned budget of $100,000 and a CPI of 0.8, your EAC is $125,000. This means that you will need $25,000 more than what you originally planned to complete your project.
Help others by sharing more (125 characters min.)
- Shreekant Karpe Program delivery manager / Agile Project Manager | SSM® 6| CSM® | PRINCE2® Foundation / Practitioner | ASP.Net MVC development | Aspiring DevOps engineer and currently specializing in Docker and Kubernetes orch
- Report contribution
Thanks for letting us know! You'll no longer see this contribution
To use AC and EV to forecast project outcomes, you need to calculate the following indicators:Cost Variance (CV) = EV - ACCost Performance Index (CPI) = EV / ACSchedule Variance (SV) = EV - PVSchedule Performance Index (SPI) = EV / PVEstimate at Completion (EAC) = BAC / CPIEstimate to Complete (ETC) = EAC - ACVariance at Completion (VAC) = BAC - EACThese indicators help you compare the planned and actual values of cost and schedule, and predict the final cost and duration of the project. They also help you identify potential issues or risks, and take corrective actions if needed.
LikeLike
Celebrate
Support
Love
Insightful
Funny
6 What are the benefits and limitations of AC and EV?
Using AC and EV can help you monitor and control your project's cost and value, and provide you with valuable insights and feedback to make informed decisions and adjustments. AC and EV can also help you communicate your project's status and health to your stakeholders, and demonstrate your accountability and transparency. However, AC and EV also have some limitations that you should be aware of. For instance, AC and EV do not reflect the quality or the customer satisfaction of your project's deliverables, which are also important aspects of value. AC and EV also depend on the accuracy and reliability of your project's plan, scope, and budget, which may change over time due to risks, changes, and uncertainties. Therefore, you should not rely solely on AC and EV, but use them in conjunction with other metrics and indicators that capture the full picture of your project's performance and value.
Help others by sharing more (125 characters min.)
- Shreekant Karpe Program delivery manager / Agile Project Manager | SSM® 6| CSM® | PRINCE2® Foundation / Practitioner | ASP.Net MVC development | Aspiring DevOps engineer and currently specializing in Docker and Kubernetes orch
- Report contribution
Thanks for letting us know! You'll no longer see this contribution
Some of the benefits and limitations of AC and EV are:AC and EV help you compare the planned and actual values of cost and schedule, and predict the final cost and duration of the project. They also help you identify potential issues or risks, and take corrective actions if needed.AC and EV require accurate and timely data collection and analysis, which can be challenging and time-consuming for complex or large-scale projects. They also depend on the quality and reliability of the baseline plan, which may change due to scope creep, change requests, or unforeseen events.AC and EV are not sufficient to measure the quality, customer satisfaction, or business value of the project. They only focus on the quantitative aspects of the project.
LikeLike
Celebrate
Support
Love
Insightful
Funny
7 Here’s what else to consider
This is a space to share examples, stories, or insights that don’t fit into any of the previous sections. What else would you like to add?
Help others by sharing more (125 characters min.)
Software Project Management
Software Project Management
+ Follow
Rate this article
We created this article with the help of AI. What do you think of it?
It’s great It’s not so great
Thanks for your feedback
Your feedback is private. Like or react to bring the conversation to your network.
Tell us more
Tell us why you didn’t like this article.
If you think something in this article goes against our Professional Community Policies, please let us know.
We appreciate you letting us know. Though we’re unable to respond directly, your feedback helps us improve this experience for everyone.
If you think this goes against our Professional Community Policies, please let us know.
More articles on Software Project Management
No more previous content
- You're facing budget overruns on your project. How can you satisfy stakeholders without sacrificing quality?
- Your team is divided on project priorities. How do you ensure resources are allocated effectively?
- Balancing competing stakeholder demands in Agile software projects: Can you prioritize tasks effectively?
- Your team is struggling with adapting to scope changes. How will you get them on board?
- Balancing user feedback and technical constraints in your project. Can you find the sweet spot for success? 4 contributions
No more next content
Explore Other Skills
- IT Strategy
- System Administration
- Technical Support
- Cybersecurity
- IT Management
- IT Consulting
- IT Operations
- Data Management
- Information Security
- Information Technology
More relevant reading
- Control Engineering You’re working on a project with limited resources. How can you make sure you meet your deadlines?
- Project Management You’re a project manager. How do you ensure your projects stay within budget?
- Project Management How do you assess project progress using earned value analysis?
- Project Management What is the most effective way to estimate project value and return on investment?