Underbillings, Overbillings and Contract Bonds - Surety Bonds by Axcess (2024)

Underbillings and Overbillings are important to all contractors and contract Surety Bond underwriters. Learn more about what they are and what underwriters look for in determining a contractor’s bond capacity.

Percentage of Completion Accounting

Most contractors should be using the Percentage of Completion (POC) method of accounting. This is the most accurate method of construction accounting and creates both Underbillings and Overbillings. You can read more about the Different types of financial statements here.

What is an Underbilling?

Underbillings are an industry name for Costs in Excess of Billings on Uncompleted Contracts. Simply put, they are revenue that a contractor has theoretically earned but not yet billed. For example, if a project is 50% complete but a contractor has only billed for 40%, the project is 10% underbilled.

The formula for calculating underbillings is:

[Total Cost Incurred to Date + Gross Profit Recognized to Date] – Total Amount Billed to Date.

Underbilling Example on a project

Here is an example. Suppose a contractor has a project valued at $1,000,000 with an Estimated Total Cost of $850,000 and Estimated Gross Profit of $150,000. The project has incurred Costs to Date of $425,000. Using the Cost-to-Cost Method (Estimated Total Cost / Cost to Date), this project is 50% complete, meaning that we have also earned 50% of the profit. Therefore, the Gross Profit Earned to Date is $75,000. In this scenario, we have billed $400,000 on the project to date. Using our underbilling formula we add the Costs to Date of $425,000 with the Gross Profit Earned to Date of $75,000. This equals $500,000 which is the Total Earned Revenue on this project. We then subtract the Billings to Date of $400,000 from the $500,000 and we get $100,000. We have a $100,000 underbilling.

If you consider the example above, the project is underbilled by $100,000 because we have earned $500,000 of revenue on this project but we have only billed for $400,000.

Underbillings on a Balance Sheet

Underbillings show up on a contractor’s Work in Progress Report. This report should tie back to a contractor’s balance sheet where Underbillings appear as a current asset. Underbillings are a Current Asset because in theory, they should be revenue that the contractor can bill for and collect in the future.

Many contract surety bond companies base a contractor’s bond capacity as a multiple of working capital. Working Capital is calculated by taking Current Assets and subtracting Current Liabilities.

In theory, because it’s a Current Asset, more underbillings should increase working capital and therefore surety bond capacity. However, this is almost never the case. You can see how Underbillings show up on a balance sheet and their relation to working capital in the sample balance sheet below.

Because we only have one project, our underbillings on the balance sheet only show the $100,000. In reality, the amount showing up on the balance sheet would be to total underbillings for all contracts in progress.

Underbillings and Bond Companies

Contract Surety Bond companies are skeptical of underbillings because they often turn into losses. From a practical standpoint, underbillings often appear when there is a project dispute, a poor estimate, or bad billing practices.

Disputes

Underbillings often happen when there is a dispute. The contractor submits a change order for work that has been done but cannot bill for it. This creates an underbilling. Contractors should ALWAYS have a signed change order in hand before doing work outside the contract.

For this reason, contract bond underwriters will closely monitor underbillings on a particular project. If the Underbilling remains for more than a billing cycle or two, most surety bond underwriters will assume it’s a loss, and remove it from their analysis.

Poor Estimate

Underbillings can also occur when a project was estimated improperly. For example, a contractor may realize they have significantly more cost than originally estimated, but the contractor may be unable to bill for those costs under the contract.

Bad Billing Practices

Underbillings also show up when a contractor has bad billing practices. If a contractor has earned revenue that is not in dispute, the contractor should be billing for it.

Constant underbillings are a sign that a contractor has poor accounting systems in place, and this is a major red flag to surety bond underwriters. Contractors often have bonds claims and go bankrupt when they have bad systems in place.

When are Underbillings Acceptable?

There are situations when Underbillings are justified. One example is when a contractor is not allowed to bill for material or equipment until it is installed.

Certain trades also tend to have more underbillings. However, these underbillings should generally be small and billed quickly.

What are Overbillings?

Overbillings are an industry term for Billings in Excess of Costs on Uncompleted Contracts. Simply put, these are revenues that a contractor has billed for, but that they have not yet earned. For example, if a contract is 50% complete and the contractor has billed for 60%, the project is 10% overbilled.

The formula for Overbillings is: Total Billings to Date – [Cost to Date + Gross Profit Earned to Date].

Overbillings Example

Using our example from earlier, let’s assume that instead of the $400,000 Billings to Date, we had actually billed $550,000 instead. Everything else stayed the same. Our Work in Progress Report would look like this:

Our project is now overbilled by $50,000. Using our formula for overbillings, we see that $550,000 has been Billed to Date. We still have Costs to Date of $425,000 and Gross Profit Earned to Date of $75,000 and we add those two together to get $500,000. We subtract this number from our $550,000 Billed to Date number and we get an overbilling of $50,000. This amount is an overbilling because we have billed more at this point in time than we have earned from our costs and profits.

Overbillings also show up on a contractor’s Work In Progress Report and should tie back to the Contractor’s balance sheet as a Current Liability. Overbillings are a Current Liability because the contractor has billed for costs and earnings on work they have not completed yet. This work will need to be completed in the future and the contractor will not be able to bill for the costs at that time.

Below shows how overbillings appear on a contractor’s balance sheet and their relationship to working capital. In this example, we only have one project. In reality, the amount showing up on a balance sheet would the total overbillings for all projects under construction.

Overbillings and Surety Bond Companies

Most contract surety bond companies view some Overbilling as a positive. It is a best practice to stay slightly ahead of Billings on a project. In fact, an accepted industry practice is to “front load” a contract to cover mobilization, insurance and performance bond costs, etc. Front loading is the process where contractors shift their schedule of values to be higher in the early stages of a project to cover upfront expenses and improve cash flow through the early parts of the project. Front loading is generally an accepted practice IF the larger early billings are reasonable. Front loading will create an overbilling.

Overbillings can be a problem for contractors though. Bond underwriters will want to make sure that a contractor has enough cash and account receivables to offset Overbillings. This is because the contractor will have a cash outflow later in the project. Not having enough cash and receivables to offset Overbillings is a sign of cash flow troubles to come.

Job Borrow

While being slightly overbilled on a project is acceptable, job borrow is not. Job Borrow occurs when a contractor uses revenue from one project to cash flow another project.

Pure Job Borrow occurs when a project is overbilled by more than the project’s remaining Gross profit. Job Borrow is often a sign of cash flow issues to contract bond underwriters and other lenders.

Learn more about underbillings, overbillings and how surety bond companies look at a Contractor’s Work in Progress Report here.

Summary

Every contractor should understand Underbillings and Overbillings. Accurate accounting and timely billing practices are vital to the success of any construction company. These practices are also essential to contractors needing contract bonds such as bid bonds, performance bonds and payment bonds. Contractors may use our free WIP Report here to help them track projects and billings.

Contact Axcess Surety anytime for best practices and help with all bond needs.

Other Frequently Asked Questions

What is an Underbilling and How is it used in Percentage-of-Completion Accounting?

An underbilling in Percentage of Completion Accounting occurs when a contractor has billed less on a project in a period than they have earned. For example, a contractor has earned 50% of the project revenue but only billed for 40%. The project would be 10% underbilled.

What is an Overbilling and How is it used in Percentage-of-Completion Accounting

An overbilling in Percentage of Completion Accounting occurs when a contractor has billed for more than they have earned on a project for a given period. For example, a contractor has earned 50% of the project revenue but has billed for 60%. The project would be 10% overbilled.

Why is Overbilling a Liability?

The contractor has billed for work that has not been completed and will have costs when they do complete the work that they will not be able to bill for again. Therefore, an overbilling shows up as a Current Liability on a balance sheet.

Why is an Underbilling an Asset?

The contractor has performed work that has not been billed and should be able to bill and collect that revenue later. Therefore, an underbilling shows up as a Current Asset on a balance sheet.

  • Author
  • Recent Posts

Josh Carson, AFSB

See Also
Revenue

Vice President at Axcess Surety

Vice President of Axcess Surety. Surety Bond and financial expert dedicated to helping contractors, businesses and individuals understand and obtain surety bond credit.

Latest posts by Josh Carson, AFSB (see all)

  • Surety Bond Countersignature Requirements - July 11, 2024
  • All Rights Letters in Surety Bonding - March 22, 2024
  • Increased Limits of the SBA Surety Bond Guarantee Program - March 6, 2024

Contents hide

1 Percentage of Completion Accounting

2 What is an Underbilling?

2.1 Underbilling Example on a project

2.2 Underbillings on a Balance Sheet

3 Underbillings and Bond Companies

3.1 Disputes

3.2 Poor Estimate

3.3 Bad Billing Practices

4 When are Underbillings Acceptable?

5 What are Overbillings?

5.1 Overbillings Example

6 Overbillings and Surety Bond Companies

7 Job Borrow

8 Summary

8.1 What is an Underbilling and How is it used in Percentage-of-Completion Accounting?

8.2 What is an Overbilling and How is it used in Percentage-of-Completion Accounting

8.3 Why is Overbilling a Liability?

8.4 Why is an Underbilling an Asset?

Underbillings, Overbillings and Contract Bonds - Surety Bonds by Axcess (2024)

FAQs

What are overbillings and underbillings? ›

If overbilling occurs, WIP reports may show a surplus, indicating that the revenue recognized exceeds the actual work completed. Conversely, in cases of underbilling, WIP reports reflect a deficit, signifying that billings are lagging behind the true percentage of work accomplished.

What is the meaning of underbillings? ›

Underbilling occurs when work you've completed hasn't been billed or costs you've incurred haven't been reimbursed. Nearly every contractor has some underbilling from time to time. But underbilling can hurt your cash flow and eat into your profits.

How to record over under billings? ›

Over/Under Billing = Total Billings – Earned Revenue.

What is the formula for underbillings? ›

The formula for calculating underbillings is: [Total Cost Incurred to Date + Gross Profit Recognized to Date] – Total Amount Billed to Date.

What is an example of overbilling? ›

Overbilling in construction primarily occurs when a contractor bills for contracted labor and materials before that work is actually completed. For example, a contractor has completed only 40% of a project but they bill for 50% of the total contract value. That means their customer pays the overbilled amount of 10%.

How to calculate overbillings and underbillings? ›

Building A Work In Progress Schedule
  1. Formula: Percentage of Completion = Total Costs Incurred / Projected Cost.
  2. Formula: Earned Revenue to Date = Percentage of Completion * Projected Revenue.
  3. Formula: Over / Under Billings = Total Billings to Date - Earned Revenue to Date.
Feb 16, 2021

What are the problems with underbilling? ›

Underbilling happens when you invoice for less than the total value of work completed in a billing cycle. Common causes of underbilling include miscalculations, missing billing cycles, unapproved change orders, and lack of organization.

What is the meaning of Overbill? ›

Meaning of overbill in English

to send someone an invoice for a greater amount than they owe: An audit concluded the company allowed systems to overbill for services. Some see this as an invitation for insurance companies to overbill the federal government. Compare. overcharge.

What is the opposite of overbilling? ›

Underbilling is the opposite of overbilling and occurs when a contractor completes a certain amount of work during a billing cycle on a project, but does not bill their customer for the entire amount of work completed during the cycle.

What is the journal entry for under billing? ›

You underbill when your actual revenue is less than your earned-to-date revenue on a job. The system creates a journal entry for a revenue account, such as Unbilled Revenue. It also creates an offsetting debit for an accrued revenue asset account.

Do underbillings increase revenue? ›

Underbilling, or "costs in excess of billing," occurs when the invoiced amount for completed work is less than the earned amount based on the project's progress. This leads to a revenue shortfall, adversely affecting cash flow and potentially the ability to fund ongoing and future initiatives.

What is underbillings to working capital? ›

Underbillings to Working Capital indicates the percentage of a company's working capital that is composed of work performed but not yet billed. Underbillings may be unreliable assets, therefore a lower ratio is preferred.

What is the difference between underbilling and overbilling? ›

Being over billed and under billed are terms commonly used in construction. They describe the difference between the amount billed by a contractor and the amount recognized as revenue. These differences arise due to various factors such as unapproved change orders, job borrowing situations, and slow billing practices.

What are underbillings on a balance sheet? ›

For example, if a contractor is 50% complete with the costs on a contract, but they have billed only 40% of the total contract price, the result would be an underbilling (a current asset on the balance sheet) in the amount of 10% of the contract price.

What is the meaning of under billing? ›

Underbilling is the opposite of overbilling and occurs when a contractor performs a certain amount of work in a billing period but does not invoice their customer for the full amount of completed work.

What is the meaning of over billing? ›

Overbilling (sometimes spelled as over-billing) is the practice of charging more than is legally or ethically acceptable on an invoice or bill.

What is the meaning of excess billing? ›

Billings in excess is a key financial term used in the construction industry. It refers to the dollar value charged to customers that is in excess of the costs and profits earned on a project to date, as explained by Businesscon.org.

Are overbillings bad? ›

Overbilling can be good for your cashflow, but it can also potentially cause problems if used in the wrong way.

Top Articles
What is Money? (Little Book, Big Idea) – Pages of Hackney
Old Money: Old Money Chronicles: Tracing the Lineage of the Upper Class - FasterCapital
Access-A-Ride – ACCESS NYC
Craigslist Free Stuff Appleton Wisconsin
Kostenlose Games: Die besten Free to play Spiele 2024 - Update mit einem legendären Shooter
Canelo Vs Ryder Directv
Erin Kate Dolan Twitter
Ella Eats
Cvs Learnet Modules
Betonnen afdekplaten (schoorsteenplaten) ter voorkoming van lekkage schoorsteen. - HeBlad
Grace Caroline Deepfake
Peraton Sso
Tnt Forum Activeboard
Billionaire Ken Griffin Doesn’t Like His Portrayal In GameStop Movie ‘Dumb Money,’ So He’s Throwing A Tantrum: Report
Van Buren County Arrests.org
Pokemon Unbound Shiny Stone Location
Evil Dead Rise Showtimes Near Regal Sawgrass & Imax
Evil Dead Rise Showtimes Near Pelican Cinemas
PCM.daily - Discussion Forum: Classique du Grand Duché
Bidevv Evansville In Online Liquid
Kohls Lufkin Tx
New Stores Coming To Canton Ohio 2022
Dr Seuss Star Bellied Sneetches Pdf
Is Light Raid Hard
R/Airforcerecruits
Salemhex ticket show3
Vistatech Quadcopter Drone With Camera Reviews
Lehpiht Shop
Where Do They Sell Menudo Near Me
Rocketpult Infinite Fuel
Honda Ruckus Fuse Box Diagram
The Syracuse Journal-Democrat from Syracuse, Nebraska
Taylor University Baseball Roster
WorldAccount | Data Protection
Keir Starmer looks to Italy on how to stop migrant boats
Craigs List Hartford
Three V Plymouth
Mitchell Kronish Obituary
Citroen | Skąd pobrać program do lexia diagbox?
Bustednewspaper.com Rockbridge County Va
Atu Bookstore Ozark
Blue Beetle Showtimes Near Regal Evergreen Parkway & Rpx
Gli italiani buttano sempre più cibo, quasi 7 etti a settimana (a testa)
Tacos Diego Hugoton Ks
Keci News
Sacramentocraiglist
Dying Light Mother's Day Roof
1Tamilmv.kids
Escape From Tarkov Supply Plans Therapist Quest Guide
La Fitness Oxford Valley Class Schedule
Latest Posts
Article information

Author: Delena Feil

Last Updated:

Views: 5803

Rating: 4.4 / 5 (65 voted)

Reviews: 88% of readers found this page helpful

Author information

Name: Delena Feil

Birthday: 1998-08-29

Address: 747 Lubowitz Run, Sidmouth, HI 90646-5543

Phone: +99513241752844

Job: Design Supervisor

Hobby: Digital arts, Lacemaking, Air sports, Running, Scouting, Shooting, Puzzles

Introduction: My name is Delena Feil, I am a clean, splendid, calm, fancy, jolly, bright, faithful person who loves writing and wants to share my knowledge and understanding with you.