Earned Value vs. Actual Costs 11 years 11 months ago #2946

  • James Pursley
  • Earned Value vs. Actual Costs (6) Topic Author
  • Offline
  • Fresh Boarder
  • Earned Value vs. Actual Costs (7)
  • Posts: 3
  • Thank you received: 0

If earned value (EV) = how much work has been accomplished on the project and Actual Cost (AC) = the true costs incurred, what is the difference between the two terms and how they relate?

Earned Value vs. Actual Costs 11 years 11 months ago #2947

  • Rachu
  • Earned Value vs. Actual Costs (8)
  • Offline
  • Junior Boarder
  • Earned Value vs. Actual Costs (9)
  • Posts: 26
  • Karma: 1
  • Thank you received: 4

Hi James,

Let me first take an example. Lets say a very small project has total BAC (budget at completion) value of USD1000 and duration estimate of 4 weeks. Following are some numbers after 2nd week of completion in the project,

The project is 40% complete. The Actual Cost incurred on the project so far is USD 350.

Now according to the duration estimate, the project should be 50% complete (2 weeks in 4 weeks duration), so the PLANNED VALUE is USD 500 (50% of total BAC of USD1000). But the project is only 40% complete so far, so the value we earned in the project, EARNED VALUE is USD400 (40% of the BAC). We also have the ACTUAL COST of USD350.

So the EV is the value we earned in the project and AC is the cost to earn that value. If AC is lower than the EV that mean we are under budget (at that point, which is the case in this example). CPI (Cost Performance Index =EV/AC) gives that value. Think about if AC is USD450 in lieu of USD350, the same project becomes over budget.

Not sure if my explanation is clear or not, experts please chime in with your valuable comments.

Regards, R.

The following user(s) said Thank You: Neeraj Vasudeva, Melanie Moore

Earned Value vs. Actual Costs 11 years 11 months ago #2949

  • Khurram Hussain
  • Earned Value vs. Actual Costs (10)
  • Visitor
  • Earned Value vs. Actual Costs (11)

Rachu’s example is correct. However, allow me to explain the underlying fundamental concept.

Projects are carried out to attain different objectives. External projects are usually carried out to earn revenue while internal projects are carried out either to earn revenue or achieve an organization’s objective or goal. Revenue analysis for the projects carried out to earn revenue is easy and you would use measures as NPV, IRR or Rate of Return to analyze these revenues. However, the majority of projects do not contribute directly to earning revenues. For example, setting up a new enterprise resource planning system for an organization doesn’t directly earn revenue of the organization. This is an internal project and the associated benefits are intangible. To analyze cost performance, a project manager needs a system that is impartial of revenue contributions of the project and is rather based on the original budget approved for the project.

The Earned Value Management system compares the cost and schedule performance of a project by comparing the current state with the approved cost and schedule baselines.

Every project eats its allocated budget to progress. If the project is eating the budget more than the planned rate, it is likely to go over budget. The Actual Cost “AC” is the budget that has been consumed to date. The Planned Value “PV” is the amount of budget that was allocated to be consumed to date. The Earned Value “EV”, is the amount of work the project has completed in reference to the original project budget “BAC”. It would have been better if we could base the EV on the actual revenues generated by the project, however as I have already explained, most of the projects do not have direct revenue contributions. Hence, the EV is a comparison against the approved budget (BAC) instead of the forecasted revenues.

To summarize, EV is the sum of the planned budget allocation for the amount of work completed to date. PV is the sum of the planned budget allocation for the amount of work “that should have been” completed to date. The difference of EV and PV will tell you about the schedule variance.

If you'll read Rachu's comment now, it should be easier to grab. Please let me know if I have been successful in explaining the core concept?

Warm regards,

Khurram Hussain, PMP, CSSBB

Earned Value vs. Actual Costs 11 years 11 months ago #2950

  • James Pursley
  • Earned Value vs. Actual Costs (12) Topic Author
  • Offline
  • Fresh Boarder
  • Earned Value vs. Actual Costs (13)
  • Posts: 3
  • Thank you received: 0

Thank you both for two very well thought out responses! Based on your explanations is still seems like that AC and EV totals will be the same at any point of the effort since even for non-revenue-generating projects you will still have costs. I get the feeling I'm still missing something. If you start back with the definition I used of EV and AC in the starting thread (i.e. EV is equal to the work that has been accomplished on the project; and, AC is equal to the true costs incurred) then maybe my beginning premise is not accurate. Doesn't EV and AC apply to both revenue-generatong AND non-revenue generating projects or is there some exclusion for either scenario that is not needed for one of the two variables?

Thank you,
Jim

Earned Value vs. Actual Costs 11 years 10 months ago #2952

  • Khurram Hussain
  • Earned Value vs. Actual Costs (14)
  • Visitor
  • Earned Value vs. Actual Costs (15)

Hi Jim:

The Earned Value Management is independent of whether project is revenue generating or not. All it considers is the approved project budget and schedule, that is the baselines.

Please also note that there are projects which do not incur direct costs, hence no AC. For example, if I am managing a project internally for my organization that requires development of a reporting system, it won’t cost me anything except me and my team’s time. One can argue that a portion of our salaries contributes to this project as its cost, but that’s indirect cost. Usually for internal projects that do not require capital investment, AC is not recorded.

Coming back to your question whether AC and EV be equal for projects having direct costs; yes they can be equal, but that will be a very rare and unlikely situation. If the project budget and schedule was very well defined, and everything goes as planned, then you might have both these values be equal.

Imagine if we are exactly completed half of the project work having an approved budget of $100,000, what would be our current EV? That is, how much ‘value’ have we earned so far in comparison to the approved budget? 50% of it right? So the EV is $50,000. Now, what is our AC? Is it $50,000 as well? No, it can’t be determined by that. AC is independent of the baselines; it is the amount we have spent so far. The AC can be $40,000 or $60,000 or anything else depending upon how much we have actually spent.

So, here are the answers to your questions:

1. No, AC and EV totals are generally not the same.
2. EV is based on the ‘value’ of work completed in comparison to the BAC.
3. AC is the actual costs incurred to date; independent of EV or BAC.
4. EV, and AC are not related to project revenues at all. Both, revenue-generating and non-revenue-generating projects have EV and AC.
5. Your definitions of EV and AC are correct.

Please feel free to let me know if I have failed again in clearing your confusion. If that’s the case, perhaps I have not understood your question. Please try rephrasing your question with some sort of an example.

Regards,

Khurram Hussain, PMP, CSSBB

Earned Value vs. Actual Costs 11 years 10 months ago #2954

  • James Pursley
  • Earned Value vs. Actual Costs (16) Topic Author
  • Offline
  • Fresh Boarder
  • Earned Value vs. Actual Costs (17)
  • Posts: 3
  • Thank you received: 0

Khurram - Thank you once again and especially for such a thorough and thoughtful reply! Your assistance is far from failing me. It is greatly helping me understand a problem area for me and what may as well be a foreign language to me - finances Earned Value vs. Actual Costs (18) . Your insight is huge help and I greatly appreciate it. I'm scheduled to sit for the exam on December 2 and along with continued review of the knowledge areas and process groups I am spending the last month or so primarily focusing on the finance and formula aspects so I will probably have more questions - fair warning Earned Value vs. Actual Costs (19) .

Thank you,
Jim

Earned Value vs. Actual Costs 11 years 10 months ago #2955

  • Khurram Hussain
  • Earned Value vs. Actual Costs (20)
  • Visitor
  • Earned Value vs. Actual Costs (21)

Thanks and best of luck for your exam Earned Value vs. Actual Costs (22)

Regards,

Khurram Hussain, PMP, CSSBB

Earned Value vs. Actual Costs 7 years 2 months ago #11215

  • a
  • Earned Value vs. Actual Costs (23)
  • Visitor
  • Earned Value vs. Actual Costs (24)

This is great explanation. Much better than the textbook.

[emailprotected] 5 years 3 months ago #17462

  • Anonymous
  • Earned Value vs. Actual Costs (25)
  • Visitor
  • Earned Value vs. Actual Costs (26)

Khurram, I have an exercise which states: a very small project has total BAC (budget at completion) value of USD100,000 and duration estimate of 5 weeks. After 2nd week of completion in the project, the project is 38% complete. According to the schedule, the project should be 48% completed. Draw the S-Curve and show PV, EV, and AC. I do not have cost incurred to date.
Thanks,
Luis

Earned Value vs. Actual Costs 4 years 10 months ago #18828

  • Crystal
  • Earned Value vs. Actual Costs (27)
  • Visitor
  • Earned Value vs. Actual Costs (28)

Thank you for this thread! I was struggling with the same thought process and take the exam this afternoon. This really cleared up the confusion!

Crystal

Earned Value vs. Actual Costs 4 years 7 months ago #19796

  • Anonymous
  • Earned Value vs. Actual Costs (29)
  • Visitor
  • Earned Value vs. Actual Costs (30)

if earned value is greater than planned value cost so in this case , is there a concern ?

Earned Value vs. Actual Costs 4 years 6 months ago #20067

  • Chetan
  • Earned Value vs. Actual Costs (31)
  • Visitor
  • Earned Value vs. Actual Costs (32)

the way you clarified that the EV is the value earned in the project and cost we put to earn it is the actual cost... clarified it all.

thanks

Earned Value vs. Actual Costs 4 years 5 months ago #20432

  • Anonymous
  • Earned Value vs. Actual Costs (33)
  • Visitor
  • Earned Value vs. Actual Costs (34)

This helped out a lot thank you!

Earned Value vs. Actual Costs 2 years 3 months ago #29509

  • Alonso Mena
  • Earned Value vs. Actual Costs (35)
  • Visitor
  • Earned Value vs. Actual Costs (36)

Could you explain why in MsProject, EV is equal to AC and you can not modify the AC?

Moderators: Yolanda Mabutas,Khurram Hussain,Mary Kathrine Padua,John Paul Bugarin,Harry Elston,Jean Kwanda,Daniel Soerensen,Alexander Anikin,Elena Zelenevskaia,Brent Lee,Christine Whitney, PMP

Earned Value vs. Actual Costs (2024)
Top Articles
Les meilleurs brokers & courtiers en bourse : Comparatif [current_year]
What is an ACH Transfer? All about ACH bank transfers | Plaid
Oldgamesshelf
Fan Van Ari Alectra
Craigslist St. Paul
Quick Pickling 101
Tesla Supercharger La Crosse Photos
7.2: Introduction to the Endocrine System
Athletic Squad With Poles Crossword
Apply A Mudpack Crossword
Prices Way Too High Crossword Clue
Keniakoop
Craigslist Pets Longview Tx
How to find cash from balance sheet?
Dirt Removal in Burnet, TX ~ Instant Upfront Pricing
Craigslist Free Stuff Merced Ca
Grayling Purnell Net Worth
Carson Municipal Code
Accident On May River Road Today
TBM 910 | Turboprop Aircraft - DAHER TBM 960, TBM 910
2024 INFINITI Q50 Specs, Trims, Dimensions & Prices
Georgetown 10 Day Weather
Qhc Learning
Like Some Annoyed Drivers Wsj Crossword
Rubber Ducks Akron Score
Mals Crazy Crab
Sorrento Gourmet Pizza Goshen Photos
6892697335
Emuaid Max First Aid Ointment 2 Ounce Fake Review Analysis
Ofw Pinoy Channel Su
Autopsy, Grave Rating, and Corpse Guide in Graveyard Keeper
Sun-Tattler from Hollywood, Florida
Human Unitec International Inc (HMNU) Stock Price History Chart & Technical Analysis Graph - TipRanks.com
Morlan Chevrolet Sikeston
Sinfuldeeds Vietnamese Rmt
Tal 3L Zeus Replacement Lid
Restored Republic December 9 2022
Section 212 at MetLife Stadium
Shane Gillis’s Fall and Rise
Tunica Inmate Roster Release
Rush Copley Swim Lessons
Craigslist Antique
How to Install JDownloader 2 on Your Synology NAS
Value Village Silver Spring Photos
Market Place Tulsa Ok
Boyfriends Extra Chapter 6
UNC Charlotte Admission Requirements
Mikayla Campinos Alive Or Dead
Lira Galore Age, Wikipedia, Height, Husband, Boyfriend, Family, Biography, Net Worth
Pilot Travel Center Portersville Photos
Wieting Funeral Home '' Obituaries
Saw X (2023) | Film, Trailer, Kritik
Latest Posts
Article information

Author: Geoffrey Lueilwitz

Last Updated:

Views: 6364

Rating: 5 / 5 (80 voted)

Reviews: 95% of readers found this page helpful

Author information

Name: Geoffrey Lueilwitz

Birthday: 1997-03-23

Address: 74183 Thomas Course, Port Micheal, OK 55446-1529

Phone: +13408645881558

Job: Global Representative

Hobby: Sailing, Vehicle restoration, Rowing, Ghost hunting, Scrapbooking, Rugby, Board sports

Introduction: My name is Geoffrey Lueilwitz, I am a zealous, encouraging, sparkling, enchanting, graceful, faithful, nice person who loves writing and wants to share my knowledge and understanding with you.