Direct and Liquidated Damages in Construction Claims
By AIA Contract Documents
February 28, 2023
There are a wide variety of claims and causes of action that may be asserted in a construction dispute. However, regardless of the type of claim or cause of action, there are generally three types of damages that can be recovered: direct, liquidated, and consequential damages. Understanding these categories can be beneficial when faced with a lawsuit.
Direct Damages
Direct damages, also known as actual damages, are those damages which are the necessary and usual result of the defendant’s wrongful act; they flow naturally and necessarily from the wrong. The aim of awarding direct damages is to compensate the plaintiff for the loss incurred that was foreseeable by the defendant from the wrongful act. In the context of construction claims, direct damages would include costs to repair or replace defective or damaged work and any additional costs incurred to complete a project in the event the Contractor failed to complete the work properly or in a timely manner.
Liquidated Damages
Liquidated damages are damages that are specified in the contract and agreed to by the parties. Liquidated damages are included in a contract to compensate for a potential breach of the contract. The amount determined in a liquidated damages clause is supposed to be a best estimate of the compensation that would be appropriate if the parties to the contract were to suffer a breach. Liquidated damages clauses typically specify certain types of breach, denoting the amount to be paid for each.
These provisions, however, are often difficult to enforce, and each jurisdiction has particular rules regarding enforceability of such provisions. One of the key factors in determining whether a liquidated damages provision can be enforced is whether the amount specified in the contract is reasonable. A liquidated damages provision that operates more as a punishment than just compensation for the loss will typically not be enforced. In making this determination, courts look to what would have been considered reasonable when the contract was formed, as opposed to when the claim actually arose.
Consequential Damages
Consequential damages, also known as special damages, relate to indirect losses or damages incurred by either party arising from a breach of contract by one of the parties. Some examples of consequential damages include lost profits or income, increased financing costs on the part of the owner, or loss of business opportunities by the contractor. The issue with consequential damages is that it is often difficult to quantify the amount of damages that a party is entitled to and the damages may be excessive compared to the overall value of the contract.
AIA Contract Documents has provided this article for general informational purposes only. The information provided is not legal opinion or legal advice and does not create an attorney-client relationship of any kind. This article is also not intended to provide guidance as to how project parties should interpret their specific contracts or resolve contract disputes, as those decisions will need to be made in consultation with legal counsel, insurance counsel, and other professionals, and based upon a multitude of factors.
FAQs
Direct damages in a construction contract refer to the losses or costs that directly result from a breach of the contract by the contractor. These damages are typically quantifiable and intended to compensate the non-breaching party for the actual harm or loss caused by the breach.
What are examples of liquidated damages in construction? ›
For example, a liquidated damages clause might state that a contractor will owe the owner $500 per day for every day past the project deadline that substantial completion is not achieved. This contractual solution can be advantageous for both parties.
How to calculate liquidated damages on a construction project? ›
CONTRACT COST X TOTAL EXTENDED COST TOTAL PROJECT COST X CONTRACT DURATION = LIQUIDATED DAMAGES
- A Linear Function of Contract Cost. ...
- An Inverse Function of Contract Time. ...
- The Extended Costs are Uniform. ...
- Milestone Application.
What are liquidated and ascertained damages in construction? ›
Liquidated damages, also known as liquidated and ascertained damages (LADs), are a contractual agreement on damages that are designed to cover costs when a project runs past the agreed completion date. LADs are common in construction, as they provide some certainty for both parties regarding the consequences of delay.
What are examples of direct damages? ›
Direct damages, on the other hand, are those damages that are a direct and immediate loss caused by a breach and compensate for that loss. Examples of direct damages include costs to repair faulty work or additional work, as well as resulting general conditions expenses and project delay costs.
What are standard construction liquidated damages? ›
What are liquidated damages in construction? Liquidated damages are funds covering the costs for each day the project continues past the agreed-upon date of completion. These funds are typically deducted from what the owner owes the contractor for the work — eating into already thin profit margins.
What are three major causes of liquidated damage? ›
states, “a provision for liquidated damages will be regarded as valid, and not a penalty when three conditions are met: (1) the damages to be anticipated from the breach are uncertain in amount or difficult to prove, (2) there was an intent by the parties to liquidate them in advance, and (3) the amount stipulated is a ...
How to negotiate liquidated damages? ›
In my experience, a good way to avoid back and forth while negotiating liquidated damages is to set caps or thresholds on liquidated damages to limit exposure. Establishing a maximum amount can also provide a sense of security for both parties while addressing concerns about excessive penalties.
What are acceptable liquidated damages? ›
For a liquidated damages clause to be upheld, two conditions must be met. The amount of the damages identified must roughly approximate the damages likely to fall upon the party seeking the benefit of the term as assessed at the time when the agreement of contract was entered into.
How to avoid paying liquidated damages? ›
To avoid this, it is crucial to establish clear and realistic timelines during the contract negotiation stage. Setting achievable milestones and allowing sufficient time for each phase of the project can help mitigate the risk of delays and subsequent imposition of liquidated damages.
The total amount of liquidated damages shall not exceed ten percent (10%) of the amount of the contract.
What is the formula for liquidated damages? ›
Liquidated damages is an amount equal to at least one tenth (1/10) of one (1) percent of the cost of the unperformed portion of the works for every day of delay.
Can liquidated damages be punitive? ›
(b) Liquidated damages are not punitive and are not negative performance incentives (see 16.402-2).
What are actual damages in construction? ›
In the context of construction claims, direct damages would include costs to repair or replace defective or damaged work and any additional costs incurred to complete a project in the event the Contractor failed to complete the work properly or in a timely manner.
Are liquidated damages enforceable? ›
As discussed above, liquidated damages provisions are enforceable only if the damages are difficult to estimate, which makes it challenging to set an amount in the contract.
What are direct and indirect damages? ›
Direct losses refer to the physical or structural impact caused by the disaster such as the destruction of infrastructure caused by the force of high winds, flooding or ground shaking. Indirect effects are the subsequent or secondary results of the initial destruction, such as business interruption losses.
What is the meaning of direct damage? ›
Direct damage is physical damage to property, as distinguished from time element loss, such as business interruption or extra expense, that results from the inability to use the damaged property.
What is the difference between direct and actual damages? ›
Direct damages, also known as actual damages, are those damages which are the necessary and usual result of the defendant's wrongful act; they flow naturally and necessarily from the wrong.
What are direct and indirect costs in construction? ›
For instance, the cost of raw materials for a construction project is a direct variable cost. Indirect variable costs impact the entire business but are not directly tied to a specific project or product. For example, utility costs (electricity, water) in a construction company's office are indirect variable costs.